83rd Street - Gleason Road to Clare Road

  • Project cost$13,671,790
  • Project schedule2024-2027
83rd Street Gleason to Clare detailed map

Project Purpose

Continued development in western Lenexa, along with potential traffic increases from the Panasonic Plant, show that 83rd Street will need capacity and safety improvements in the next five years. The current street is a two-lane road without adequate shoulders, stormwater system and street lighting.

Project Description

The City of Lenexa has included funding for improvements to 83rd Street from Clare Road to Gleason Road in its 2024 – 2028 Capital Improvement Program. Conceptual design is underway. However, due to the size and complexity of the project, construction is not scheduled to begin until spring 2027. The tentative project schedule follows:

Phase  Start Duration
 Design Phase Services  Spring 2024  24 months
 Public Meeting Fall 2024  
 Right-of-way Acquisition  Summer 2025 12 months
Utility Relocations Spring 2026

12 months

 Bid Project Winter 2026  
 Begin Construction Spring 2027 12-14 months

Detailed map

83rd Street Gleason to Clare detailed map

 


Design Phase

The City has engaged HNTB Corporation to provide engineering services. The project design will be divided into two phases:

Design Phase 1

Phase 1 will be focused on engineering surveys, traffic study, high-level concept designs, and cost estimates for 83rd Street from Gleason Road to Clare Road. 

Phase 1 will also include traffic and high-level concept analysis of the broader 83rd Street Study Corridor from Clare Road to the western Lenexa city limits (Exhibit A). These results will allow us to establish roadway geometrics and schedules for implementing these improvements.

The contract completion date for Phase 1 is August 30, 2024.  

Upon completion of Phase 1, results of the analysis will be provided and your input solicited during one-on-one meetings with affected property owners as well as a public meeting.  

Design Phase 2

Phase 2 will take the Phase 1 selected alternative (Clare Road to Gleason Road) and prepare detailed plans, specifications, and cost estimates. 


Field Survey

HNTB has subcontracted with Kaw Valley Engineering (KVE) for surveying services. KVE will perform field surveys including field locating utilities and full topography survey encompassing the project limits between Clare Road and Gleason Road.

The survey work may require access to your property by the surveyors, who will be in identifiable safety vests. 