The stormwater system in this area has reached the end of its useful life. The project is part of the City’s ongoing efforts to maintain and upgrade its infrastructure. The project has received County Stormwater Management Program funding, which reduces City costs.
The project will replace a 83" x 57" corrugated metal pipe under Bluejacket, immediately north of 87th Street. The project will line or replace existing smaller pipes along Melrose Drive in the nearby Pine Ridge Business Park.
October 2026: Project is complete.
February 2026: Project is under construction. Will finish in summer 2026.