89th Terrace to 90th Street Stormwater Improvements

  • Project typeStormwater
  • Project cost$3,223,500
  • Project schedule2025–2026
89th Terrace to 90th Street - west of Lackman Road map

Project purpose

The stormwater system in this area has reached the end of its useful life. The project is part of the City’s ongoing efforts to maintain and upgrade its infrastructure. The project has received County Stormwater Management Program funding, which reduces City costs.


Project description

The project will replace or line the existing stormwater system to restore its condition to acceptable levels. 

Work will take place May through fall 2026.


Current status

July 2025: Easement acquisition underway.

February 2026: Will award contract on March 3 and then fabricate structures.