Woodsonia Drive - 83rd Street to Prairie Star Parkway Project

  • Project typeStreets / Bridges / Traffic
  • Project cost$10,077,000
  • Project schedule2025–2026
  • Contractor nameCohorst Enterprises; Phelps Engineering, Inc.; Emery Sapp & Sons
Woodsonia Drive from 83rd Street to Prairie Star Parkway improvements map

Project purpose

A special benefit district was established to support infrastructure improvements needed to serve new development.


Project description

The project includes construction of Woodsonia Drive from the intersection of Woodsonia Drive and Prairie Star Parkway north approximately 4,500 feet to the existing Woodsonia Drive, along with completion of a 575-foot gap near Westside Family Church between two existing roadway sections. Improvements will include landscaping, stormwater, concrete curb and gutter, sidewalks and streetlights.

Phase I

This phase of work will construct Woodsonia Drive from 87th Street to 600 feet north.

Phase II

This phase of work will construct Woodsonia Drive from Prairie Star Parkway to 89th Street.


Current status

July 2026:

  • Phase I of work is complete.
  • Phase II project was designed by Phelps Engineering, Inc., and construction is anticipated to be complete by summer 2027.
  • Lenexa City approved a construction bid award to Emery Sapp & Sons on July 7.