Green Prairie Subdivision Street Reconstruction Project

  • Project typeStreet Reconstruction
  • Project cost$5.5 million
  • Project scheduleConstruction: 2025
  • Contractor nameStreet reconstruction - Amino Brothers; Water main - Kissick Construction
Green Prairie Subdivision street reconstruction map

Project description

The Green Prairie Subdivision Street Reconstruction Project will completely rebuild most streets within the subdivision, as well as a small section of Summit Street northeast of the area. The roads have exceeded their useful life, and traditional maintenance strategies, such as mill and overlays, are no longer effective due to rapid deterioration.

This project will also include significant utility upgrades. The City will work in partnership with WaterOne, which will upgrade a large section of water main as part of the project. Additional utility work will be handled by outside companies and contractors.

After the utility work is completed, the project will involve the removal of the existing roadway, installation of new water mains and water service connections, subgrade modifications, spot replacement of sidewalks and curbs, upgrades to streetlights, and installation of new asphalt pavement.

Green Prairie Subdivision Street Reconstruction Map(PDF, 7MB)


Current status

Aug. 22, 2025:

Water main installation – The contractor has completed installation of the new water main and will finish the remaining tie-ins to the old main and all service lines installations over the next couple of weeks. Service line work will take place on 93rd Street, Cottonwood Street and Widmer Road.

Concrete operations – Concrete work will resume on Monday, Aug. 25. Crews will remove and replace curb and gutter at three main locations: 

  • North side of 92nd Terrace (from just west of Mullen Road to Cottonwood Street)
  • East side of Cottonwood Street (from 92nd Terrace to 93rd Terrace) 
  • West side of Cottonwood Street (from 93rd Terrace to Old 95th Street)  

Removals are planned for Monday and Tuesday, with new concrete placed on Wednesday. Driveway access will be restored once the concrete has reached the required strength, which is anticipated by Friday afternoon.

Street reconstruction – Phase 2 of street reconstruction will be completed Monday, Aug. 25. This work will consist of paving the next 2 inches of asphalt. The final 2 inches will be placed near the end of the project.

Streetlight installation – All underground work is complete. Installation of new lights is planned for early October.


Project phasing

Green Prairie Subdivision Construction Phases Map(PDF, 6MB)


Cost and funding sources

Total cost: $5.5 million

Funding sources: Capital Improvement Fund – Pavement Reconstruction Program. See the 2025-2029 Capital Improvement Program for details.


Timeline

Utility modifications: February to June 2025

Final design: March 2025

Bid opening: March 2025

City construction starts: May 2025


Project team

Engineering Design and Inspection: GBA

Construction Contractors:

  • Street reconstruction - Amino Brothers
  • Water main - Kissick Construction

Reasons for complete reconstruction

The City and its consultant have reviewed the asphalt and underlying base material (subgrade) on all the streets throughout the Green Prairie Subdivision. The leading issue is related to the asphalt pavement and base material that consists of a reclaimed aggregate base and a thin layer of asphalt. This thin layer of asphalt has not held up well over time.  Additionally, the team found that the subgrade soils mostly consist of a well-compacted fill made of clay and sand with spot locations of overly saturated clay. The saturated clay locations leads to some spot failures but is not the main reason for issues along the roadway. 

The best long-term strategy is to completely replace the roadway. This includes removing unsuitable soil, densifying the subgrade, installing an aggregate base, and finally installing the base and surface asphalt. 


Frequently asked questions

When can I remove the flags in my yard?

The flags mark underground utilities and are essential for contractors performing investigation or relocation work. Removing them could result in utility disruptions for you or your neighbors. Please leave the flags in place and work around them if construction crews are in your area.